Application

  • Submit Application Form to MPOB by Group Manager or  Applicant
  • MPOB review application, determine the type of premises
    • Premise category I - site without recognized sustainable standard certification
    • Premise category II - site with attained the recognized sustainable standard certification
  • Pass the input to CB
  • CB reviews application and interact with premises
    • Through Basic Data
    • Determine standard for certification
    • Determine type of certification
      • Individual certificate
      • Group Management certification
    • Conduct study
      • Risk management initial review
      • Stakeholder review
  • Audit plan will be generated
  • Where 'group certification' is applied, random sampling will follow according to S=r√n Risk factor
  • Sampling methodology in accordance to IAF MD 1:2007 – IAF Mandatory Document for the Certification of Multiple Sites Based on Sampling

Stage 1 Audit

  • Stage 1 audit can be skipped for the site under category premise II
  • CB will schedule Stage I audit
  • Audit Plan will submit to auditee
  • Adequacy of MSPO documentation
  • Raise issues of concern in Stage I audit report
  • 6 months interval gap between Stage I and Stage II or otherwise stage 1 shall repeat
  • CB will conduct external stakeholder consultation Report endorsed by both parties
  • Stakeholder issues shall be verified during Stage II audit
  • Schedule the Stage II audit once issues of concern are resolved

Stage 2 Audit

  • Verify implementation of MSPO system
  • Type of audit findings – non conformities and observations
  • Audit findings raised during closing meeting
  • Draft report sent to auditee within 30 days after Stage II
  • Auditee take corrective actions submit report within 60 days
  • CB reviews, accept, verifies corrective actions
  • Satisfactory resolution of audit findings 
  • CB prepares report within 14 days
  • Failure to do corrective action within 60 days  discontinuation MSPO Certification 
  • Repeat stage II audit if the premise fail to resolve the issues
  • Issuance of certificate with 5 years validity 

Surveillance Audit

  • Annual assessment done by CB
  • Total 4 surveillance audit must be conducted before re-certification will take place

Re-certification Audit

  • Same process as per Stage II audit